Contractor: Torpoint Construction Ltd Job: Metal stud work, plaster board adhesive fixed system (dot and dab) plaster finish

 

Perrys Vauxhall required full fit out to renovate their garage at Huddersfield. We started by erecting a jumbo stud wall formed from 92mm MF Stud work spanning 32 metres x 4 metres. We braced and placed timbers to the main back wall to stabilise the stud work.

 

This had to be insulated and double boarded and skimmed using gypsum products. We then started forming new offices, a canteen and staff areas.

 

Forming new walls using Gypsum 70 C stud, fireline plasterboard and skim finish. The C stud track was screwed down to the concrete floor for stability, and fixed to existing roof line at the top of the track.

 

Vertical studs are all fixed and screwed into place ready to receive plasterboard. Once the plasterboards are fixed in place, we then applied the joint tape and board finish coating.